Overview
At 298-bed OSF HealthCare Little Company of Mary Medical Center in Illinois, Pointcore helped OSF open an electrophysiology lab on schedule using our program management and construction management approaches. Faced with a mechanical unit that had a 40-week lead time which threatened the launch date, our team acted swiftly to re-engineer the solution. We reduced lead time to only 13 weeks while maintaining ongoing hospital operations without disruption.
Throughout the project we leveraged our healthcare-specific construction experience, proactive procurement strategy and trusted partner network to deliver on time and ahead of occupancy approval.
Read more about the details of this project here.
Key Highlights
- 67.5% reduction in mechanical unit delivery time
- 3-month reduction in Illinois Department of Public Health (IDPH) occupancy approval
- Part of a larger phased project
Client
OSF HealthCare
Location
Evergreen Park, IL
Our approach
Program Management/Owner Representation, Construction Management
Services Used
Preconstruction Planning, Construction Services